Create or Edit a Stage

To add a new Stage, click on “Add a New Stage” or to edit a Stage, click on

...

“Edit Stage”.

...

The “Duration Value” can be a number like “15” which means the stage will be 15 days long. If a number is entered such as “15.6:20” it means the stage is 15 days, 6 hours and 20 minutes long (dd.hh:mm).

...

Stage Duration Type can be ‘Time Based’ (in days) or ‘Formula Based’. Time Based stays open for the set amount of days once initiated.

...

Formula Based is triggered by a variable set in the study design.

...

Panel
bgColor#DEEBFF

Create a Schedule

...

To see existing schedules in a stage, click the “+” button to the left of the row.

...

Image Added

The row will expand and show the existing schedules within the stage.

...